Clyde Bike Cage

Global Administrator -

A W Edwards were the Principal Contractor for the construction of the Sydney Trains Central Hub project and subcontracted LEDA to supply and install a secure bike parking enclosure.

The project brief was to provide Securabike parking for space up to 40 cyclists in a weatherproof cage, weld mesh modular panels and access door with pin code entry, free to exit door hardware as well as internal solar lighting. LEDA designed and manufactured a fully roofed structure based on our UBC03 design, incorporating a wide centre aisle and CBR4SC compact racks fitted to opposing sides of the 7m x 5.4m enclosure. Because the site did not have mains power to the cage area a lithium battery powered multi pin code door lock was fitted and meant that each bike user was provided with their own personal user code of access.



  • Bunnings-green
  • Canberra
  • Macquarie_Australia_logo
  • sponsors-grey-deakin
  • BovisLendLease